Aug
13
Jul
16
to 18 Jul
Review Draft condition Resource Consent
Draft conditions have been given by MPDC, Thomas and Harvinder are reviewing conditions and negotiating for best outcomes.
Jul
16
to 24 Jul
Storm water design
Tilsley Engineering is preparing a stormwater plan to satisfy MPDC needs
Jul
16
to 24 Jul
Geotechnical Report
Tilsley Engineering is preparing a short from Geotechnical report for liquifaction risks
Jul
14
CKL transport teams meeting with MPDC Council
Judith is having a teams call with MPDC to go through their final questions.
Jun
22
Traffic Impact Assessment
CKL Engeneering is preparing a TIA report for resource consent
Jun
9
to 22 Jun
Jun
5
to 11 Jun
Fire report for transportable building
AssetCare is writing a fire report on transportable building for building consent. Which will advise us on where detectors should be placed once teh building is on site.
May
7
to 9 May
Affected persons signatures
Collecting signatures from 1081 Morrinsville Walton road, 1018 Morrinsville Walton Road and 17 Chepmell Road
Mar
26
to 31 May