August

  1. Resource consent approval

  2. Building consent approvals

September

  1. Open enrolments online

  2. Hire staff

  3. Signage

  4. Carpark

  5. Septic system

  6. Covered walkway

  7. Foundations

  8. Water tanks cleaned

  9. Buildings delivered

  10. Window safety films installed

  11. Internal renovations

  12. Set up spaces

October

  1. Set up spaces

  2. Fencing

  3. Building WOF

  4. Health inspection

  5. Pre licensing

  6. Open day for marketing

November

  1. Open day